2,00,000 SQ. FT. It Building Bult in just 11 months

Everest is one of India's fastest growing complete building solutions company. The Pre-engineered Buildings division of the company has successfully delivered more than 2000 PEB structures in last half a decade across the country for large as well as mid-scale manufacturing and infrastructure companies. Today Everest ships out one Pre-Engineered Building every day from its manufacturing facilities in Dahej and Bhagwanpur. Continuing its commitment to deliver Speed, Strength and Safety.

Everest has recently delivered its first PEB building for IT sector - the office and skill development Centre buildings for IT conglomerate HCL at IT Park, Lucknow, Despite the challenges, the PEB team was yet again able to stay away from cost overruns and delays and the construction was delivered well before time and to the exact requirements of the clients.

The Challenge

  • Construction of two modern multi-storey buildings including a Skill Development centre
  • Each building had to be G+2 with full mezzanine and deck concrete slab
  • Total combined area 2, 00,000 sq.ft.
  • A conventional structure was to be redesigned and replaced by a complete Pre-engineered Steel Building
  • Delivery time was 12 months

The Solution

  • Customized the design of a conventional structure to meet the design requirements of PEB structure
  • Employed a day-wise erection plan for effective monitoring
  • Judicious material management and logistic planning ensured sequential delivery of material onsite
  • Planned coordination with other agencies working in parallel for timely execution
  • Best quality LGSF, Boards, ACP materials, Glass etc used to meet the requirements of a modern IT Infra
  • The project was accomplished using cutting edge technologies and multiple products from Everest.

Result

  • Delivered the 2 Lac sq. ft. infrastructure in just 11 months
  • This is a specially structure, first of its kind IT building built by Everest
  • Training in the Skill Development Centre and operations at the office building starts within stipulated time.